Project
A new purpose built catering and kitchen facility to the ground floor, with the upper floor providing a flexible dining or multi-purpose area.
- Client: The John Lyon School
- Location: Harrow, Middlesex
- Year: 2011
- Total Value: £1.4m
- Services Value: £400k
- Duties: Performance Duties
Design Team
- Project Manager: BPM Project Management
- Architect: The Malcolm Payne Group
- Quantity Surveyor: Rider Levitt Bucknall
- Structural Engineer: Alan Wood Partnership
- Main Contractor: Speller Metcalfe
- Electrical Contractor: A.J Taylor Electrical
- Mechanical Contractor: Stewart Harries Ltd