The works at Alamo constituted two phases. The first was to rationalise the existing electrical site infrastructure. The second was the construction of a new factory extension to house machine testing facilities and a new mechanical paint plant.
- Client: Alamo Manufacturing Services (UK)
- Location: Salford Priors near Evesham
- Year: 2014
- Total Value £4m
- Services Value: £500k
- Duties: Performance
Design Team
- Project Manager: Harris Lamb
- Architect: Harris Lamb
- Quantity Surveyor: Harris Lamb
- Structural Engineer: -
- Main Contractor: A&H Construction
- Electrical Contractor: PH Adams / CKW
- Mechanical Contractor: Gill Mechanical